|
During Restoration from Start to Finish . . . |
This page documents the progress being made on the restoration of the station.
For Latest pictures Click here
(click on individual pictures for larger images, then click "Back" button to return)
|
Photos below of the work being done to repair the Up platform wall which has been our major project over the last few months.
All Photos & Info below Copyright © John Axe - Infrastructure Team Leader - unless otherwise stated.
Maintenance Team Report June 09 The major project undertaken by the maintenance team has been the clearing and levelling of the Picnic area. This was made possible by the hiring of a 1.5 ton digger on three occasions the last being a 5 days effort. We have removed something in the order of 500 tons of material to reach our goal, the dumper doing sterling work in moving all this material to various dumping points. Some clearing and landscaping has also been carried out near the Greenhouse. The total cost to the Trust so far has been £70 for the provision of diesel fuel.
The reporting of noxious smells from the cess-pit caused the rapid arrangement of a total suction clean out by a local contractor at a cost of £95. The final cleaning was carried out by hand and the broken remains of the pipe work which should have been connected to the outlet pipe were found at the bottom of the pit. This was replaced by a new plastic pipe which should prevent any smells escaping in the future. The opportunity was also taken to remove the old un-sealed manhole which required three men to open it safely and replace it with a modern light weight sealed type at a cost of approximately £35. The old manhole and its surround was loaded into the scrap skip with the digger.
Some of the other tasks completed have been the provision of a water tap for the tea urn in the Waiting Room and the installation of a power point for coolers. A ramp of ballast has also been built to facilitate the moving of the wagon to allow access to the shunter. An un-switched spur from the power point in the Porters hut has been provided for the deep freeze to prevent inadvertent defrosting.
Future tasks include the landscaping of the Picnic area and its surrounds plus the provision of public access steps at the end of the station building. The path to the side gate will also be diverted to connect with the ramp up to the Picnic area to provide disabled access. When the platform wall is completed a drainage pipe will be installed at its base and the area backfilled and landscaped. The ramp to the Porters hut and the wall leading to the signal box are also due to receive attention. The proposed installation of an ice cream cooler in the Waiting Room will probably require the installation of a further power point. The Station gardeners have also asked for the installation of a water tap adjacent to the garden area. |
||||||||||
|
Derek Baker & Wurzle and a general view of the wall 2nd April |
Wurzle (& Derek's arm) & a general view of the wall 2nd April |
Concrete base for new wall being laid, Bill Munden on the mixer 8th April |
Base completed 8th of April |
Wurzle delivering a load of blocks using our dumper 23 April |
Dave Clark digging out the base of the trackside wall near the signal box 21 May |
|||||
|
Infrastructure Team Report July/September 09
Most of the work has been directed towards the completion of the repairs to the UP platform wall. Half the wall has been completed apart from the capping bricks and the end ramp. The subsoil drainage pipe for this area has also been installed but connection to the site storm water drain remains outstanding. The new foundations for the rest of the wall incorporating many tons of concrete have been completed and the re-building of the wall has started. Unfortunately our builder has not been able to spend as much time on the wall as he would have liked coupled with wet weather on several occasions has delayed progress somewhat. As part of this exercise the storm water drain from the Office end of the station has been diverted to go into the new drains which take any seepage away from the back of the new wall. Derek Baker and Alex Barnes have spent many hours cleaning the old capping bricks so that they can be re-used thus saving the cost of new ones (68p each).
Problems with the dumpers hydraulic steering and tipping system were rapidly diagnosed as being caused by water in the hydraulic oil. The system was stripped down, a blocked inlet filter cleared and all the contaminated oil drained out. The system was then re-filled with fresh oil, fitted with new filters and the dumper put back into service.
The “Vicars” gate in the boundary fence just beyond our official boundary has been cleared and repainted by Wurzle (Terry England) as authorised by the Trailway Rangers. This was greeted with great delight by the Vicar who made a donation to our funds in recognition of Wurzle’s work. We are still working on clearing and repairing the drains in this area.
Work has started on removing the rails etc from the cattle dock so that the bed level may be lowered to match the new track work on the rest of the site.
We have collected two lorry loads of wood and other redundant building materials from Wurzle’s work site for which we are very grateful.
We have almost completed the purchase of a large hydraulic excavator for use on various projects around the site. This will replace the machines which we have hired in the past. Owning our own machine will make our work parties more effective as the machine will be available whenever required. |
||||||||||
|
The station end of the platform wall under construction |
Footings for new garden retaining wall |
Our "new" (35 year old) Priestman Mustang digger arriving |
Delivery a bit further advanced |
Mustang being unloaded |
If we are very lucky the builder will come on Wednesday & Thursday to complete the construction of the wall. He's been coming for the last four weeks but we live in hope! |
|||||
|
The bulk of the Platform wall rebuilding is now complete with much of the back filling done. It now remains to complete the compensator box in the middle of the wall, the joint between the old and new walls and the ramp at the far end. We also have to connect the drainage pipe for the far end to the main site drain. - John |
||||||||||
|
Derek Baker compacting the Back fill behind the further part of the wall |
Yours truly giving the Mustang a bit of TLC |
Our bricklayer Derek working on the Platform wall with Bill Munden on the shovel |
Filling behind the new wall with ballast for drainage. The further section has been completed |
|||||||
|
Infrastructure Team Report September/October 09 The new digger was delivered to site on the 16th of September. The first job for it was to remove the concrete sleepers from the Cattle Dock and stack them tidily to one side. This threw up two problems, the original single lever steering control didn’t work very well and one of the bucket motions was very slow. We have converted the steering to the more conventional twin lever system. The slow bucket movement was found to be due to a broken weld within the control linkage which has been repaired. The machine will require some TLC and a repaint in due course.
The footings for the new Garden retaining wall have been dug out and concrete poured to form the wall foundation. We hope to construct the wall in the near future.
A number of holes in the platform canopy have been filled so that we can shelter from the rain without getting wet. At the same time various leaks in the guttering on the Porters Hut were sealed. Work is also in progress to provide an outside water tap in the yard behind the Gents Loo.
Work has also continued on the reconstruction of the Up platform wall including the cutting out of damaged bricks in the compensator box ready for keying into the new brickwork. The main portion of the wall has now been completed, fitted with drains and backfilled. The compensator box has been partially rebuilt up to the roof level ready to replace the roof beams which were made from old rails.
We are hoping to complete the platform wall in the next few weeks and complete the re-laying of the platform surface. This will allow the track bed to be cleared ready for lowering to its final level. We also hope to remove the Ash tree stumps and re-profile the bank to give clearance for track laying.
The small side wall in the cattle dock has been removed as it would have prevented the sleepers being re-laid in their new position. The bed level will be lowered as soon as possible so that the track can be re-laid. The cess pit and drainage system is still giving rise to problems and we are investigating whether it would be possible to connect to the local sewer system. |
||||||||||
|
Compensator Box in the middle of the Up platform wall partly reconstructed |
The completed Compensator box: this closes the gap between the two new section of Up Platform wall |
Derek Baker and Bill Munden cleaning up platform edge blocks read for re-laying. New blocks would cost in excess of 60p each! |
Derek our bricklayer starting to close the gap between the old and new sections of the platform wall. |
|||||||